The Progress Line is a function of Primavera which allows users to graphically represent a variance between a set of user defined data points in the Gantt chart.
Data Points can be chosen by right-clicking in the Gantt chart and selecting “Bar Chart Options”.
![turning-on-the-progress-line-1](https://drmcnatty.com/wp-content/uploads/2017/04/turning-on-the-progress-line-1.jpg)
Select the progress line tab and choose the Baseline in which you will be comparing against.
![turning-on-the-progress-line-2](https://drmcnatty.com/wp-content/uploads/2017/04/turning-on-the-progress-line-2.jpg)
It can be quickly turned on by selecting the “Progress Line” icon.
![turning-on-the-progress-line-3](https://drmcnatty.com/wp-content/uploads/2017/04/turning-on-the-progress-line-3.jpg)
In this example on Line 5, we can see the variance comparing our Planned Start vs. our Actual Start Dates.